nerdexam
CompTIA

CV0-004 · Question #305

During project initiation, a project manager needs to identify goals and deliverables that should be completed by the end of the project and also meet certain cost and time factors. Which of the…

The correct answer is C. Project success criteria. Project success criteria are the standards used to evaluate whether a project has met its goals within cost, time, and quality boundaries. These are defined early in initiation and form part of governance to ensure alignment with business value. WBS and milestones come later…

DevOps fundamentals

Question

During project initiation, a project manager needs to identify goals and deliverables that should be completed by the end of the project and also meet certain cost and time factors. Which of the following would best align with these needs?

Options

  • AWork breakdown structure
  • BChange log
  • CProject success criteria
  • DMilestone chart

How the community answered

(44 responses)
  • A
    9% (4)
  • B
    2% (1)
  • C
    84% (37)
  • D
    5% (2)

Explanation

Project success criteria are the standards used to evaluate whether a project has met its goals within cost, time, and quality boundaries. These are defined early in initiation and form part of governance to ensure alignment with business value. WBS and milestones come later during planning and scheduling.

Topics

#Project management#Project initiation#Success criteria#Goal setting

Community Discussion

No community discussion yet for this question.

Full CV0-004 Practice