Which of the following would help a project manager identify that project goals have been reached?

The correct answer is B. Key performance indicators. KPIs (Key Performance Indicators) are measurable values tied to project goals. If KPIs are being met, the PM can confirm that the project outcomes align with objectives. Audit reports verify compliance, while lessons learned capture knowledge at project closure.

Operations

Question

Which of the following would help a project manager identify that project goals have been reached?

Options

  • AAudit report
  • BKey performance indicators
  • CBacklog
  • DLessons learned

How the community answered

(55 responses)
  • A
    2% (1)
  • B
    91% (50)
  • C
    2% (1)
  • D
    5% (3)

Explanation

KPIs (Key Performance Indicators) are measurable values tied to project goals. If KPIs are being met, the PM can confirm that the project outcomes align with objectives. Audit reports verify compliance, while lessons learned capture knowledge at project closure.

Topics

#Project Management#KPIs#Performance Measurement#Goal Achievement