The correct answer is A: Rollback plans. A key element of change control is having a rollback plan, which allows recovery to a previous stable state if the change causes instability. This is part of operational support to maintain service availability and minimize downtime during updates.

Operations

Question

Which of the following is part of software change control?

Options

  • ARollback plans
  • BMaintenance windows
  • CValidation checks
  • DRequirements definition

Explanation

A key element of change control is having a rollback plan, which allows recovery to a previous stable state if the change causes instability. This is part of operational support to maintain service availability and minimize downtime during updates.

Topics

#Change control#Rollback#IT operations#Risk management