A systems engineer is migrating a batch of 25 VMs from an on-premises compute cluster to a public cloud using the public cloud's migration agent. The migration job shows data copies at a rate of…
The correct answer is A. The on-premises VM host hardware utilization. The engineer should review the on-premises VM host hardware utilization first. A decrease in transfer rate after a batch of migrations could suggest that the host hardware resources (like CPU, RAM, or network bandwidth) are becoming saturated, which would slow down additional
Question
A systems engineer is migrating a batch of 25 VMs from an on-premises compute cluster to a public cloud using the public cloud's migration agent. The migration job shows data copies at a rate of 250Mbps. After five servers migrate, the data copies at a rate of 25Mbps. Which of the following should the engineer review first to troubleshoot?
Options
- AThe on-premises VM host hardware utilization
- BThe on-premises ISP throttling rate
- CThe IOPS on the SAN backing the on-premises cluster
- DThe compute utilization of the VMs being migrated
How the community answered
(28 responses)- A57% (16)
- B11% (3)
- C7% (2)
- D25% (7)
Explanation
The engineer should review the on-premises VM host hardware utilization first. A decrease in transfer rate after a batch of migrations could suggest that the host hardware resources (like CPU, RAM, or network bandwidth) are becoming saturated, which would slow down additional