The sales department is preparing to launch a high-demand product for purchase through the company's online store. The senior engineer asks the junior engineer to review the sales cloud resources to p
The correct answer is D. Propose additional hosts for cluster 2.. In cluster 2 the CPU is 75% and RAM 80%, it need new servers on cluster.
Operations
Question
The sales department is preparing to launch a high-demand product for purchase through the company's online store. The senior engineer asks the junior engineer to review the sales cloud resources to plan for a surge in online traffic:
Given the metrics in the table above, which of the following resources should be adjusted to plan for future growth?
Options
- APropose additional memory for cluster 1.
- BPropose additional storage for cluster 1.
- CPropose additional guests for cluster 2.
- DPropose additional hosts for cluster 2.
How the community answered
(40 responses)- A13% (5)
- B8% (3)
- C25% (10)
- D55% (22)
Explanation
In cluster 2 the CPU is 75% and RAM 80%, it need new servers on cluster.
Topics
#capacity planning#cluster resources#traffic surge#auto-scaling