CV0-003 · Question #429

The sales department is preparing to launch a high-demand product for purchase through the company's online store. The senior engineer asks the junior engineer to review the sales cloud resources to…

The correct answer is D. Propose additional hosts for cluster 2. In cluster 2 the CPU is 75% and RAM 80%, it need new servers on cluster.

Operations

Question

The sales department is preparing to launch a high-demand product for purchase through the company's online store. The senior engineer asks the junior engineer to review the sales cloud resources to plan for a surge in online traffic:

Given the metrics in the table above, which of the following resources should be adjusted to plan for future growth?

Options

  • APropose additional memory for cluster 1.
  • BPropose additional storage for cluster 1.
  • CPropose additional guests for cluster 2.
  • DPropose additional hosts for cluster 2.

How the community answered

(40 responses)
  • A
    13% (5)
  • B
    8% (3)
  • C
    25% (10)
  • D
    55% (22)

Explanation

In cluster 2 the CPU is 75% and RAM 80%, it need new servers on cluster.

Topics

#capacity planning#cluster resources#traffic surge#auto-scaling

Community Discussion

No community discussion yet for this question.