CV0-003 · Question #208
An administrator is tasked with the virtualization of all database management applications. Which of the following should the administrator do FIRST to ensure that database performance will be…
The correct answer is C. Adhere to the recommendations of the virtualization software vendor. Before virtualizing database workloads, the virtualization platform vendor's requirements must be satisfied first to ensure the underlying infrastructure can support optimal performance.
Question
An administrator is tasked with the virtualization of all database management applications. Which of the following should the administrator do FIRST to ensure that database performance will be optimal?
Options
- AFollow the recommendations of the database management application vendor.
- BDesign a physical to virtual migration plan of the application.
- CAdhere to the recommendations of the virtualization software vendor.
- DDevelop a migration plan to the new environment, ensuring maximum uptime.
How the community answered
(26 responses)- A4% (1)
- C88% (23)
- D8% (2)
Why each option
Before virtualizing database workloads, the virtualization platform vendor's requirements must be satisfied first to ensure the underlying infrastructure can support optimal performance.
Database vendor recommendations address application-level tuning and resource sizing, which are applied after the virtualization platform is correctly configured and verified to support the workload.
Designing a physical-to-virtual migration plan is a later planning step that depends on first understanding the virtualization platform's technical requirements and constraints.
The virtualization software vendor provides platform-level requirements and configuration guidelines - such as supported guest OS versions, vCPU allocation limits, memory overhead, and storage I/O settings - that define the hard constraints of the environment before any workload-specific tuning can occur. These foundational recommendations must be satisfied first, as they govern what configurations are supported and what performance is achievable within the virtual environment. Failing to adhere to them can result in unsupported configurations and degraded or unpredictable database performance.
Developing a migration plan focused on uptime is a project execution step that follows after the technical performance and compatibility requirements of the virtualization platform have been established.
Concept tested: Virtualization vendor best practices before workload migration
Source: https://docs.vmware.com/en/VMware-vSphere/8.0/vsphere-resource-management/GUID-98BD5A8A-260A-494F-BAAE-74781F5C4B87.html