Which of the following should an administrator establish before deploying a guest VM in a production environment?

The correct answer is C. Business continuity plan. Before deploying a guest VM in a production environment, a Business Continuity Plan (BCP) should be established to define how the VM supports ongoing operations and what procedures apply if it becomes unavailable.

Deployment

Question

Which of the following should an administrator establish before deploying a guest VM in a production environment?

Options

  • ADisaster recovery plan
  • BPatch management schedule
  • CBusiness continuity plan
  • DAccess control list

How the community answered

(24 responses)
  • A
    4% (1)
  • C
    92% (22)
  • D
    4% (1)

Why each option

Before deploying a guest VM in a production environment, a Business Continuity Plan (BCP) should be established to define how the VM supports ongoing operations and what procedures apply if it becomes unavailable.

ADisaster recovery plan

A Disaster Recovery Plan focuses narrowly on restoring IT systems after a major incident and is a component of the broader BCP, which should be established first to provide the overarching continuity context.

BPatch management schedule

A patch management schedule is an operational procedure applied after the VM is live and does not need to be established as a prerequisite before deployment.

CBusiness continuity planCorrect

A Business Continuity Plan defines how critical systems - including newly deployed VMs - support ongoing business operations and specifies the procedures and requirements needed if those systems fail. Establishing the BCP before deployment ensures that redundancy, failover, and availability requirements are incorporated into the VM design from the outset. Without a BCP, a production VM may be deployed without adequate consideration for its business impact or recovery expectations.

DAccess control list

An Access Control List is a specific network or resource security configuration, not a planning framework that must be established before a VM goes into production.

Concept tested: Business continuity planning before production VM deployment

Source: https://nvlpubs.nist.gov/nistpubs/Legacy/SP/nistspecialpublication800-34r1.pdf

Topics

#business continuity plan#guest VM deployment#pre-deployment planning

Community Discussion

No community discussion yet for this question.

Full CV0-003 Practice