A cloud engineer needs to deploy a new virtual firewall in a private cloud. Which of the following should the engineer do as a FIRST step?

The correct answer is B. Create a change for deploying the firewall. Before deploying a new virtual firewall in a private cloud, the crucial first step is to formally initiate the change management process. This ensures proper planning, approval, and risk assessment are conducted.

Deployment

Question

A cloud engineer needs to deploy a new virtual firewall in a private cloud. Which of the following should the engineer do as a FIRST step?

Options

  • ADocument the deployment in a knowledge base.
  • BCreate a change for deploying the firewall.
  • CPut the hypervisor in maintenance mode.
  • DInform users that the cloud will be momentarily unavailable.

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    73% (16)
  • C
    14% (3)
  • D
    9% (2)

Why each option

Before deploying a new virtual firewall in a private cloud, the crucial first step is to formally initiate the change management process. This ensures proper planning, approval, and risk assessment are conducted.

ADocument the deployment in a knowledge base.

Documenting the deployment is typically done after planning or during/after execution, not as the very first step before initiating the process.

BCreate a change for deploying the firewall.Correct

Creating a change for deploying the firewall is the foundational first step in any structured IT environment to ensure that the deployment follows organizational policies, undergoes necessary approvals, and is properly documented for accountability and risk mitigation. This formal process prevents unauthorized changes and maintains service stability.

CPut the hypervisor in maintenance mode.

Putting the hypervisor in maintenance mode is a technical execution step performed much later, likely during the actual deployment window, not as the initial planning phase.

DInform users that the cloud will be momentarily unavailable.

Informing users about service unavailability is a communication step taken closer to the actual deployment, after the change has been approved and scheduled, not as the initial action.

Concept tested: Change management process initiation

Source: https://learn.microsoft.com/en-us/azure/cloud-adoption-framework/manage/considerations/change-management

Topics