nerdexam
CompTIA

CV0-002 · Question #395

Which of the following types of disaster recovery sites will have the highest MTTR if needed for operations during an outage?

The correct answer is D. Cold site. A cold site will have the highest Mean Time To Recover (MTTR) because it requires significant time for equipment acquisition, installation, and data restoration before operations can resume.

Operations

Question

Which of the following types of disaster recovery sites will have the highest MTTR if needed for operations during an outage?

Options

  • AWarm site
  • BGeoclustered site
  • CRedundant site
  • DCold site

How the community answered

(30 responses)
  • A
    7% (2)
  • B
    3% (1)
  • D
    90% (27)

Why each option

A cold site will have the highest Mean Time To Recover (MTTR) because it requires significant time for equipment acquisition, installation, and data restoration before operations can resume.

AWarm site

A warm site has some hardware and network connectivity pre-installed, reducing the time needed for setup compared to a cold site, thus resulting in a lower MTTR.

BGeoclustered site
CRedundant site
DCold siteCorrect

A cold site is a basic facility equipped only with space, power, and cooling, lacking pre-installed hardware, software, or current data backups. In a disaster, the organization must acquire and install all necessary equipment, configure systems, and restore data, which makes the recovery process lengthy, resulting in the highest MTTR.

Concept tested: Disaster recovery site types and MTTR

Source: https://learn.microsoft.com/en-us/compliance/regulatory/offering-disaster-recovery-business-continuity