A task cannot begin before another task is completed. How is this described in a project task schedule?
The correct answer is B. dependency. See the full explanation below for the reasoning.
AV Installation
Question
A task cannot begin before another task is completed. How is this described in a project task schedule?
Options
- Arequirement
- Bdependency
- Cconsequence
- Ddetermination
How the community answered
(26 responses)- A12% (3)
- B81% (21)
- C4% (1)
- D4% (1)
Topics
#task dependency#project scheduling#project management#critical path