A task cannot begin before another task is completed. How is this described in a project task schedule?

The correct answer is B. dependency. See the full explanation below for the reasoning.

AV Installation

Question

A task cannot begin before another task is completed. How is this described in a project task schedule?

Options

  • Arequirement
  • Bdependency
  • Cconsequence
  • Ddetermination

How the community answered

(26 responses)
  • A
    12% (3)
  • B
    81% (21)
  • C
    4% (1)
  • D
    4% (1)

Topics

#task dependency#project scheduling#project management#critical path