A crucial part of the bid (tender) process is the request for clarification. At what point in the bid (tender) process would a potential bidder submit a request for clarification?

The correct answer is C. After the bid (tender) specifications are received, but before the proposals are due. See the full explanation below for the reasoning.

AV Installation

Question

A crucial part of the bid (tender) process is the request for clarification. At what point in the bid (tender) process would a potential bidder submit a request for clarification?

Options

  • AAfter the award, but before the job begins
  • BAfter proposals are submitted, but before the award
  • CAfter the bid (tender) specifications are received, but before the proposals are due
  • DAfter the walkthrough, but before the bid (tender) specification package is sent out

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    16% (6)
  • C
    76% (29)
  • D
    5% (2)

Topics

#bid process#tender process#RFP#request for clarification

Community Discussion