Avixa
CTS · Question #170
What is defined by a work breakdown structure (WBS)?
The correct answer is A. Project scope. See the full explanation below for the reasoning.
AV Installation
Question
What is defined by a work breakdown structure (WBS)?
Options
- AProject scope
- BProject budget
- CProject schedule
- DProject resources
How the community answered
(38 responses)- A82% (31)
- B5% (2)
- C3% (1)
- D11% (4)
Topics
#WBS#project scope#project management#planning
Community Discussion