CTFL_UK · Question #86

During which test activity could faults be found most cost effectively?

The correct answer is C. Planning. See the full explanation below for the reasoning.

Question

During which test activity could faults be found most cost effectively?

Options

  • AExecution
  • BDesign
  • CPlanning
  • DCheck Exit criteria completion

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    84% (26)
  • D
    10% (3)