Which of the following is a project risk mitigation step you might take as test manager? 1 credit
The correct answer is C. Arranging a back-up test environment in case the existing one fails during testing. Topic 5, Scenario 5, V1"Human Resource System" You have recently been employed as a test manager for a software house producing Human Resource (HR) systems, namely Payroll, Personnel and Recruitment systems. The company is relatively new and wants to make a major impact in the…
Question
Which of the following is a project risk mitigation step you might take as test manager? 1 credit
Options
- ATesting for performance problems
- BHiring a contractor after a test analyst leaves the company
- CArranging a back-up test environment in case the existing one fails during testing
- DPerforming a project retrospective meeting using the test results after each increment
How the community answered
(22 responses)- A18% (4)
- B5% (1)
- C73% (16)
- D5% (1)
Explanation
Topic 5, Scenario 5, V1"Human Resource System" You have recently been employed as a test manager for a software house producing Human Resource (HR) systems, namely Payroll, Personnel and Recruitment systems. The company is relatively new and wants to make a major impact in the market by producing a worldwide enterprise HR product.