nerdexam
ISTQB

CTFL_UK · Question #65

Given is the following defect removal chart reported at the end of system testing - showing total defects detected and closed defects (fixed and successfully retested). A number of open defects are…

The correct answer is D. Another system test cycle to verify defect resolution. See the full explanation below for the reasoning.

Question

Given is the following defect removal chart reported at the end of system testing - showing total defects detected and closed defects (fixed and successfully retested). A number of open defects are classified as critical. All tests have been executed. Based on the chart above, what is the most appropriate next test phase? 1 credit

Exhibit

CTFL_UK question #65 exhibit

Options

  • AAcceptance testing to verify the business process
  • BAcceptance testing to verify operational requirements
  • CRequirements testing as part of testing regulatory compliance
  • DAnother system test cycle to verify defect resolution

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    14% (4)
  • C
    4% (1)
  • D
    79% (22)

Community Discussion

No community discussion yet for this question.

Full CTFL_UK Practice