Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits

The correct answer is A. Create an estimate based on the function point analysis technique and test point analysis. Topic 10, Scenario 10, V3 "Online Application" The cancellation of a current major development project has released resources. The development manager has decided to respond to his own request to tender and has proposed an in-house development with the use of a Rapid…

Test Management

Question

Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits

Options

  • ACreate an estimate based on the function point analysis technique and test point analysis
  • BCreate an estimate based on the complexity of the code
  • CCreate an estimate based on the credentials of the successful bidder
  • DCreate an estimate based on a percentage of the development effort

How the community answered

(42 responses)
  • A
    79% (33)
  • B
    2% (1)
  • C
    14% (6)
  • D
    5% (2)

Explanation

Topic 10, Scenario 10, V3 "Online Application" The cancellation of a current major development project has released resources. The development manager has decided to respond to his own request to tender and has proposed an in-house development with the use of a Rapid Application Development (RAO) approach.