Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits
The correct answer is A. Create an estimate based on the function point analysis technique and test point analysis. Topic 10, Scenario 10, V3 "Online Application" The cancellation of a current major development project has released resources. The development manager has decided to respond to his own request to tender and has proposed an in-house development with the use of a Rapid…
Question
Which one of the following estimation approaches is appropriate at this stage of the project? 2 credits
Options
- ACreate an estimate based on the function point analysis technique and test point analysis
- BCreate an estimate based on the complexity of the code
- CCreate an estimate based on the credentials of the successful bidder
- DCreate an estimate based on a percentage of the development effort
How the community answered
(42 responses)- A79% (33)
- B2% (1)
- C14% (6)
- D5% (2)
Explanation
Topic 10, Scenario 10, V3 "Online Application" The cancellation of a current major development project has released resources. The development manager has decided to respond to his own request to tender and has proposed an in-house development with the use of a Rapid Application Development (RAO) approach.