Which aspect in the test estimate is the main risk in this project? 1 credit

The correct answer is D. Unknown input quality due to third party development. Topic 8, Scenario 8, V1 "Test Process Improvement" You have been asked to investigate various test process Improvement models to be introduced for the next project. You have been asked to provide a comparison between the TMMi and TPI models and provide a recommendation.

Test Management

Question

Which aspect in the test estimate is the main risk in this project? 1 credit

Options

  • AQuality of the specification
  • BAvailability of end-users
  • CThe costs of hardware and tools
  • DUnknown input quality due to third party development

How the community answered

(56 responses)
  • A
    16% (9)
  • B
    7% (4)
  • C
    4% (2)
  • D
    73% (41)

Explanation

Topic 8, Scenario 8, V1 "Test Process Improvement" You have been asked to investigate various test process Improvement models to be introduced for the next project. You have been asked to provide a comparison between the TMMi and TPI models and provide a recommendation.