CTFL_UK · Question #40
Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project. 2 credits (for 2 out of 3 correct 1 credit)
The correct answer is A. Test planning, test case preparation and test execution for each of the four iterations B. Work should be explicitly allocated to test completion, test management, installation and to training on using D. Regression testing in the second, third and fourth iterations. See the full explanation below for the reasoning.
Question
Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project. 2 credits (for 2 out of 3 correct 1 credit)
Options
- ATest planning, test case preparation and test execution for each of the four iterations
- BWork should be explicitly allocated to test completion, test management, installation and to training on using
- CActivities to deploy the system in the user environment
- DRegression testing in the second, third and fourth iterations
- EDevelopment activities for unit and integration testing
- FReviews on requirements documentation
- GDefining test environment requirements for system testing
How the community answered
(29 responses)- A83% (24)
- C3% (1)
- E10% (3)
- F3% (1)
Community Discussion
No community discussion yet for this question.