CTFL_UK · Question #37
Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits
The correct answer is B. Criteria A = NOT OK, criteria B = NOT OK, criteria C = OK. Topic 6, Scenario 6, V4 "Independent Test Team" You have for a while been trying to hire a second test automation specialist for your test team However, you did not have any luck in finding a suitable candidate. So now, you have been asked by IT management of XYZ to forward a…
Question
Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits
Options
- ACriteria A = OK, criteria B = OK, criteria C = OK
- BCriteria A = NOT OK, criteria B = NOT OK, criteria C = OK
- CCriteria A = OK, criteria B = NOT OK, criteria C = NOT OK
- DCriteria A = NOT OK, criteria B = NOT OK, criteria C = NOT OK
How the community answered
(22 responses)- A5% (1)
- B77% (17)
- C14% (3)
- D5% (1)
Explanation
Topic 6, Scenario 6, V4 "Independent Test Team" You have for a while been trying to hire a second test automation specialist for your test team However, you did not have any luck in finding a suitable candidate. So now, you have been asked by IT management of XYZ to forward a proposal with alternative solutions for building an automated regression test suite at system test level over a period of 2 years including needed training and eventual handover to the test team.
Topics
Community Discussion
No community discussion yet for this question.