Which of the following is a valid drawback of independent testing? 1 credit
The correct answer is B. Developers loose the sense of responsibility and independent testers may become a bottleneck. See the full explanation below for the reasoning.
Question
Which of the following is a valid drawback of independent testing? 1 credit
Options
- ADeveloper and independent testing will overlap and waste resources.
- BDevelopers loose the sense of responsibility and independent testers may become a bottleneck.
- CIndependent testers need extra education and always cost more.
- DIndependent testers will become a bottleneck and introduce problems in incident management.
How the community answered
(24 responses)- A4% (1)
- B79% (19)
- C4% (1)
- D13% (3)