Which of the following would you expect to see in the master test plan? 1 credit
The correct answer is C. The test approach that will be applied at system integration testing. See the full explanation below for the reasoning.
Question
Which of the following would you expect to see in the master test plan? 1 credit
Options
- AA description of how the test cases are cross-referenced to requirements in the test management tool.
- BA detailed identification of the resources that will carry out structural testing in the first iteration.
- CThe test approach that will be applied at system integration testing.
- DA list of the names of the testers who will carry out the performance testing for the final iteration.
How the community answered
(23 responses)- A4% (1)
- B4% (1)
- C83% (19)
- D9% (2)