During the software development process, at what point can the test process start?

The correct answer is C. When the software requirements have been approved. See the full explanation below for the reasoning.

Question

During the software development process, at what point can the test process start?

Options

  • AWhen the code is complete.
  • BWhen the design is complete.
  • CWhen the software requirements have been approved.
  • DWhen the first code module is ready for unit testing

How the community answered

(47 responses)
  • A
    4% (2)
  • B
    15% (7)
  • C
    74% (35)
  • D
    6% (3)