CTFL_UK · Question #111

Hand over of Testware is a part of which Phase:

The correct answer is C. Test Closure Activities. See the full explanation below for the reasoning.

Question

Hand over of Testware is a part of which Phase:

Options

  • ATest Analysis and Design
  • BTest Planning and control
  • CTest Closure Activities
  • DEvaluating exit criteria and reporting

How the community answered

(19 responses)
  • A
    11% (2)
  • B
    16% (3)
  • C
    68% (13)
  • D
    5% (1)

Community Discussion

No community discussion yet for this question.