CTFL_SYLL_4.0 · Question #64

The following chart represents metrics related to testing of a project that was competed. Indicate what is represented by tie lines A, B and the axes X.Y A. B. C. D.

The correct answer is D. X - Time Y - Count A - Total number of executed tests B - Number of open bugs. Option D correctly explains what is represented by the lines A, B and the axes X, Y in a testing metrics chart. According to option D: X-axis represents Time Y-axis represents Count Line A represents Number of open bugs Line B represents Total number of executed tests This…

Managing the Test Activities

Question

The following chart represents metrics related to testing of a project that was competed. Indicate what is represented by tie lines A, B and the axes X.Y A. B. C. D.

Exhibit

CTFL_SYLL_4.0 question #64 exhibit

Options

  • AX - Time Y - Cost A - Cost of test (per week) B - Cost of finding a single bug (per week)
  • BX - Time Y - Number of defects A - Number of open defects B - Number of closed defects
  • CX - Time Y - Percent A - % of of functional tests in the test suite B - % of non-functional tests in the test suite
  • DX - Time Y - Count A - Total number of executed tests B - Number of open bugs

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    15% (4)
  • C
    7% (2)
  • D
    74% (20)

Explanation

Option D correctly explains what is represented by the lines A, B and the axes X, Y in a testing metrics chart. According to option D: X-axis represents Time Y-axis represents Count Line A represents Number of open bugs Line B represents Total number of executed tests This information is essential in understanding and analyzing the testing metrics of a completed

Topics

#test metrics#defect tracking#test monitoring#burn-down charts

Community Discussion

No community discussion yet for this question.