nerdexam
iSQI

CTFL_SYLL_4.0 · Question #31

CTFL_SYLL_4.0 Question #31: Real Exam Question with Answer & Explanation

Sign in or unlock CTFL_SYLL_4.0 to reveal the answer and full explanation for question #31. The question stem and answer options stay visible for context.

Question

Following a risk-based testing approach you have designed 10 tests to cover a product risk with a high-risk level. You want to estimate, adopting the three-point test estimation technique, the test effort required to reduce the risk level to zero by executing those 10 tests. You made the following three initial estimates: - most optimistic = 6 person hours - most likely = 30 person hours - most pessimistic = 54 person hours Based only on the given information, which of the following answers about the three-point test estimation technique applied to this problem is true?

Options

  • AThe final estimate is between 22 person hours and 38 person hours
  • BThe final estimate is exactly 30 person hours because the technique uses the initial most likely
  • CThe final estimate is between 6 person hours and 54 person hours
  • DThe final estimate is exactly 30 person hours because the technique uses the arithmetic mean of

Unlock CTFL_SYLL_4.0 to see the answer

You've previewed enough free CTFL_SYLL_4.0 questions. Unlock CTFL_SYLL_4.0 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full CTFL_SYLL_4.0 Practice