The correct answer is D. Unknown input quality due to third party development. Topic 8, Scenario 8, V1 "Test Process Improvement" You have been asked to investigate various test process Improvement models to be introduced for the next project. You have been asked to provide a comparison between the TMMi and TPI models and provide a recommendation.
Question
Which aspect in the test estimate is the main risk in this project? 1 credit
Options
- AQuality of the specification
- BAvailability of end-users
- CThe costs of hardware and tools
- DUnknown input quality due to third party development
Explanation
Topic 8, Scenario 8, V1 "Test Process Improvement" You have been asked to investigate various test process Improvement models to be introduced for the next project. You have been asked to provide a comparison between the TMMi and TPI models and provide a recommendation.
Community Discussion
No community discussion yet for this question.