A new system is about to be developed. Which of the following functions has the highest level of risk?
The correct answer is A. Likelihood of failure = 20%; impact value = ?00,000. In (B) the product of probability ?impact has the value ?5,000; in (C) the value is ?,000 and in (D) it is ?,000. The value of ?0,000 in (A) is therefore the highest.
Test Management
Question
A new system is about to be developed. Which of the following functions has the highest level of risk?
Options
- ALikelihood of failure = 20%; impact value = ?00,000
- BLikelihood of failure = 10%; impact value = ?50,000
- CLikelihood of failure = 1%; impact value = ?00,000
- DLikelihood of failure = 2%; impact value = ?00,000
How the community answered
(55 responses)- A84% (46)
- B9% (5)
- C5% (3)
- D2% (1)
Explanation
In (B) the product of probability ?impact has the value ?5,000; in (C) the value is ?,000 and in (D) it is ?,000. The value of ?0,000 in (A) is therefore the highest.
Topics
#risk assessment#risk-based testing#likelihood vs impact#product risk