nerdexam
ISTQB

CTFL18 · Question #275

What factors should be considered to determine whether enough testing has been performed? (i)The exit criteria. (ii)The budget. (iii)How big the test team is. (iv)The product's risk profile. (v)How…

The correct answer is A. i and ii and iv and vi. See the full explanation below for the reasoning.

Question

What factors should be considered to determine whether enough testing has been performed? (i)The exit criteria. (ii)The budget. (iii)How big the test team is. (iv)The product's risk profile. (v)How good the testing tools are. (vi)Sufficient details of the system status to allow decisions

Options

  • Ai and ii and iv and vi
  • Bi and ii and iii and vi
  • Cii and iii and iv and v
  • Di and ii and v and vi

How the community answered

(27 responses)
  • A
    70% (19)
  • B
    4% (1)
  • C
    7% (2)
  • D
    19% (5)

Community Discussion

No community discussion yet for this question.

Full CTFL18 Practice