Which of the following risks represents the highest level of risk to the project?
The correct answer is B. Likelihood of failure = 10%, potential cost of impact = $500,000. See the full explanation below for the reasoning.
Question
Which of the following risks represents the highest level of risk to the project?
Options
- ALikelihood of failure = 1%, potential cost of impact = $1m.
- BLikelihood of failure = 10%, potential cost of impact = $500,000.
- CLikelihood of failure = 20%, potential cost of impact = $150,000.
- DLikelihood of failure = 5%, potential cost of impact = $500,000.
How the community answered
(34 responses)- A3% (1)
- B79% (27)
- C12% (4)
- D6% (2)