nerdexam
ISTQB

CTFL18 · Question #274

Which of the following risks represents the highest level of risk to the project?

The correct answer is B. Likelihood of failure = 10%, potential cost of impact = $500,000. See the full explanation below for the reasoning.

Question

Which of the following risks represents the highest level of risk to the project?

Options

  • ALikelihood of failure = 1%, potential cost of impact = $1m.
  • BLikelihood of failure = 10%, potential cost of impact = $500,000.
  • CLikelihood of failure = 20%, potential cost of impact = $150,000.
  • DLikelihood of failure = 5%, potential cost of impact = $500,000.

How the community answered

(34 responses)
  • A
    3% (1)
  • B
    79% (27)
  • C
    12% (4)
  • D
    6% (2)

Community Discussion

No community discussion yet for this question.

Full CTFL18 Practice