CTAL-TTA_001 · Question #23
Part 1 "Test Techniques various" As part of a risk analysis, technical risks are analyzed. Which TWO factors influence technical risk? 1 credit [K2]
The correct answer is A. Complexity of technology C. Interfacing and integration issues. A (Complexity of technology) and C (Interfacing and integration issues) are correct because both are inherent properties of the technical implementation itself - they describe characteristics of the system's architecture and components that directly increase the probability or…
Question
Part 1 "Test Techniques various" As part of a risk analysis, technical risks are analyzed. Which TWO factors influence technical risk? 1 credit [K2]
Options
- AComplexity of technology
- BFrequency of use of the affected failure
- CInterfacing and integration issues
- DDamage to image
- ELack of reasonable workaround
How the community answered
(26 responses)- A92% (24)
- B4% (1)
- D4% (1)
Explanation
A (Complexity of technology) and C (Interfacing and integration issues) are correct because both are inherent properties of the technical implementation itself - they describe characteristics of the system's architecture and components that directly increase the probability or impact of technical failures during development and testing.
B (Frequency of use) describes how often a failure mode occurs, which is a metric used in risk evaluation (likelihood), not a factor that defines whether a risk is technical in nature.
D (Damage to image) is a business/reputational impact - it describes a consequence of a risk materializing, not a factor that makes a risk technical.
E (Lack of reasonable workaround) speaks to the severity of a risk's impact (how recoverable the situation is), again a risk evaluation criterion, not a source of technical risk.
Memory tip: Think "technical risk = something about the thing being built." Complexity (how hard the tech is) and integration (how the pieces connect) are properties of the system itself - anything about consequences, frequency, or business impact belongs in a different risk dimension.
Topics
Community Discussion
No community discussion yet for this question.