nerdexam
iSQI

CTAL-TM_UK · Question #54

You are the Test Manager of a new project that will have three formal levels of testing. unit, integration and system testing. The testing strategy you decide to adopt a blend of risk-based testing…

The correct answer is C. Your test team executes scripted tests designed and implemented before the execution of the. See the full explanation below for the reasoning.

Question

You are the Test Manager of a new project that will have three formal levels of testing. unit, integration and system testing. The testing strategy you decide to adopt a blend of risk-based testing and reactive testing strategies. Which of the following answers describes the most consistent example of implementation of this test strategy during the execution of the system tests?

Options

  • AYour test team executes exploratory tests following a session-based test management
  • BYour test team executes system tests under the guidance of a sample of users throughout the
  • CYour test team executes scripted tests designed and implemented before the execution of the
  • DYour test team autonomously performs some exploratory testing sessions and, at the very

How the community answered

(54 responses)
  • A
    6% (3)
  • B
    13% (7)
  • C
    80% (43)
  • D
    2% (1)

Community Discussion

No community discussion yet for this question.

Full CTAL-TM_UK Practice