CTAL-TM_UK · Question #18

You are the Test Manager of a project that adopts a V-model with four formal levels of testinG. unit, integration, system and acceptance testing. On this project reviews have been conducted for each…

The correct answer is A. Number of defects found during the requirements review E. Total number of defects attributable to requirements, found during functional specification. See the full explanation below for the reasoning.

Question

You are the Test Manager of a project that adopts a V-model with four formal levels of testinG. unit, integration, system and acceptance testing. On this project reviews have been conducted for each development phase prior to testing, which is to say that reviews of requirements, functional specification, high-level design, low-level design and code have been performed prior to testing. Assume that no requirements defects have been reported after the release of the product. Which TWO of the following metrics do you need in order to evaluate the requirements reviews in terms of phase containment effectiveness?

Options

  • ANumber of defects found during the requirements review
  • BTotal number of defects attributable to requirements found during unit, integration, system and
  • CTotal number of defects found during functional specification review, high-level design review,
  • DTime to conduct the requirements review
  • ETotal number of defects attributable to requirements, found during functional specification

How the community answered

(27 responses)
  • A
    85% (23)
  • B
    4% (1)
  • C
    7% (2)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.