CTAL-TM_UK · Question #13
Assume you have some data related to confirmation testing during system testing of a past project. In that project 240 bug reports have been opened once, 80 were opened twice, 10 were opened three…
The correct answer is A. 300 person-hours have been spent on the project during the system testing phase, because. See the full explanation below for the reasoning.
Question
Assume you have some data related to confirmation testing during system testing of a past project. In that project 240 bug reports have been opened once, 80 were opened twice, 10 were opened three times and no bug reports have been opened more than three times. You estimate that a bug report, which has failed its confirmation test, costs, on average, 3 person- hours. Which of the following statements correctly describe the value of these confirmatory testing activities based on cost of quality?
Options
- A300 person-hours have been spent on the project during the system testing phase, because
- B340 person-hours have been spent on the project during the system testing phase, because
- C340 person-hours have been spent on the project during the system testing phase, because
- D300 person-hours have been spent on the project during the system testing phase, because
How the community answered
(18 responses)- A83% (15)
- B6% (1)
- C11% (2)