CTAL-TM_SYLL2012 Exam Questions
63 real CTAL-TM_SYLL2012 exam questions with expert-verified answers and explanations. Page 2 of 2.
- Question #52
You are a Test Manager working for a software organization where reviews have never been applied. After a meeting with your managers examining a business case for reviews, (includi...
- Question #53
You are the Test Manager for a project to develop a client-server application that allows wine vendors to order custom-assorted packages of wines of several winemakers to sell spec...
- Question #54
You are the Test Manager of a new project that will have three formal levels of testing. unit, integration and system testing. The testing strategy you decide to adopt a blend of r...
- Question #55
You are the Test Manager of a new project aimed at developing a software system that must be certified at level B of the DO-178B standard. The project will follow a V-Model softwar...
- Question #56
Based on the historical data of 5 past and similar projects, you have calculated these average numbers of defects detected in system testinG. - For each 10000 LOC (lines of code),...
- Question #57
You are estimating the effort for the integration testing activities of a new project. Consider the following factors, which can affect that estimation:
- Question #58
Assume that you are the Test Manager for a small insurance application development project. You have decided to adopt a risk-based testing strategy: 5 product risks (R1, R2, R3, R4...
- Question #60
Assume that the following test cases have been executed at the end of the first week of test execution: TC-001, TC-002 and TC-007. All these tests are `passes'. What is the MINIMUM...
- Question #61
You can count on well-written requirements, but you can't count on an adequate contribution of the stakeholders to the quality risk analysis. You have to mitigate the insufficient...
- Question #62
During the follow-up phase the following conditions are checked: X1. The code has been completely reviewed X2. All the identified defects have been correctly fixed and the modified...
- Question #63
Assume you are managing the system testing phase of a project. The system test execution period is scheduled to twenty weeks. All tests are manual tests. You are following a risk-d...
- Question #64
You are performing a quality risk analysis for a CSCI (Computer Software Configuration Item) used to implement a CBIT (Continuous Built-In Test) module of a safety-critical system....
- Question #65
Assume you are working on a CAS (Conditional Access System) for Pay-TV that allows the access, selection and transfer of services and media to authorized users. Authorized users ca...