Question
You are the Test Manager of a new project that will have three formal levels of testing. unit, integration and system testing. The testing strategy you decide to adopt a blend of risk-based testing and reactive testing strategies. Which of the following answers describes the most consistent example of implementation of this test strategy during the execution of the system tests?
Options
- AYour test team executes exploratory tests following a session-based test management
- BYour test team executes system tests under the guidance of a sample of users throughout the
- CYour test team executes scripted tests designed and implemented before the execution of the
- DYour test team autonomously performs some exploratory testing sessions and, at the very