CTAL-TM_001 · Question #41
In general which part of the testing activity is most difficult to estimate? 1 credit
The correct answer is B. Test execution. See the full explanation below for the reasoning.
Question
In general which part of the testing activity is most difficult to estimate? 1 credit
Options
- ATest planning
- BTest execution
- CTest management
- DTest design
How the community answered
(50 responses)- A4% (2)
- B78% (39)
- C6% (3)
- D12% (6)