Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits
The correct answer is B. Criteria A = NOT OK, criteria B = NOT OK, criteria C = OK. See the full explanation below for the reasoning.
Question
Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits
Options
- ACriteria A = OK, criteria B = OK, criteria C = OK
- BCriteria A = NOT OK, criteria B = NOT OK, criteria C = OK
- CCriteria A = OK, criteria B = NOT OK, criteria C = NOT OK
- DCriteria A = NOT OK, criteria B = NOT OK, criteria C = NOT OK
How the community answered
(44 responses)- A5% (2)
- B70% (31)
- C16% (7)
- D9% (4)