Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits

The correct answer is B. Criteria A = NOT OK, criteria B = NOT OK, criteria C = OK. See the full explanation below for the reasoning.

Question

Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits

Options

  • ACriteria A = OK, criteria B = OK, criteria C = OK
  • BCriteria A = NOT OK, criteria B = NOT OK, criteria C = OK
  • CCriteria A = OK, criteria B = NOT OK, criteria C = NOT OK
  • DCriteria A = NOT OK, criteria B = NOT OK, criteria C = NOT OK

How the community answered

(44 responses)
  • A
    5% (2)
  • B
    70% (31)
  • C
    16% (7)
  • D
    9% (4)