Which of the following is a valid drawback of independent testing? 1 credit
The correct answer is B. Developers loose the sense of responsibility and independent testers may become a. See the full explanation below for the reasoning.
Question
Which of the following is a valid drawback of independent testing? 1 credit
Options
- ADeveloper and independent testing will overlap and waste resources.
- BDevelopers loose the sense of responsibility and independent testers may become a
- CIndependent testers need extra education and always cost more.
- DIndependent testers will become a bottleneck and introduce problems in incident management.
How the community answered
(39 responses)- A8% (3)
- B74% (29)
- C13% (5)
- D5% (2)