CTAL-TAE · Question #9

You are planning the pilot for an in-house developed Test Automation solution (TAS). Which two of the following would be important steps to take as part of the planning process?

The correct answer is B. b and d. Ensuring developer commitment (b) is critical for successful deployment, especially in in-house solutions that may require support or integration work. Developing a project plan with allocated budget and resources (d) is also essential for effective execution of the pilot…

Deployment Risks and Contingencies

Question

You are planning the pilot for an in-house developed Test Automation solution (TAS). Which two of the following would be important steps to take as part of the planning process?

Options

  • Aa and b.
  • Bb and d.
  • Cc and d.
  • Dc and e.
  • EAsk the developers to provide any missing functionality during the deployment activities.

How the community answered

(58 responses)
  • A
    5% (3)
  • B
    83% (48)
  • C
    9% (5)
  • D
    2% (1)
  • E
    2% (1)

Explanation

Ensuring developer commitment (b) is critical for successful deployment, especially in in-house solutions that may require support or integration work. Developing a project plan with allocated budget and resources (d) is also essential for effective execution of the pilot, ensuring it is properly scoped and managed.

Topics

#pilot planning#TAS deployment#automation pilot#test planning

Community Discussion

No community discussion yet for this question.