Which task is NOT considered the responsibility of the Test Analyst as part of the test Implementation activities?

The correct answer is C. Creating automated tests or identifying tests to be automated. See the full explanation below for the reasoning.

Question

Which task is NOT considered the responsibility of the Test Analyst as part of the test Implementation activities?

Options

  • AUpdating the traceability between the test basis and testware.
  • BCreating a test execution schedule, including resource allocation.
  • CCreating automated tests or identifying tests to be automated.
  • DReporting defects based on the failures observed.

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    79% (19)
  • D
    13% (3)