You work for an insurance company that is running several parallel projects. You have been asked to advise on the best approach for test case design for each project. Project C has been experiencing…
The correct answer is D. Project C - Low level test cases. Project D - Low level test cases. See the full explanation below for the reasoning.
Question
You work for an insurance company that is running several parallel projects. You have been asked to advise on the best approach for test case design for each project. Project C has been experiencing quality issues with the requirements documentation. In previous releases, the requirements were perceived to be vague and inconsistent, prompting many time- consuming questions from the test analysts during analysis and design. For the current release, more formal requirements reviews have been introduced to try and improve quality. Project D has recognised the need for better regression testing and it is expected that 80% of the test cases created in the next release will form part of the regression pack. The regression tests will be run manually with a plan to introduce automation for future releases. What should your recommendation be with respect to the level of test case design for projects C and D?
Options
- AProject C - High level test cases. Project D - High level test cases.
- BProject C - High level test cases. Project D - Low level test cases.
- CProject C - Low level test cases. Project D - High level test cases.
- DProject C - Low level test cases. Project D - Low level test cases.
How the community answered
(22 responses)- A5% (1)
- B9% (2)
- C14% (3)
- D73% (16)