Which term defines the process of project compliance with policies and procedures?
The correct answer is B. Quality audits. See the full explanation below for the reasoning.
Question
Which term defines the process of project compliance with policies and procedures?
Options
- AQuality assurances
- BQuality audits
- CQuality control
- DQuality control management
How the community answered
(29 responses)- A10% (3)
- B83% (24)
- C3% (1)
- D3% (1)