Which of the processes includes all activities of the performing organization that determines policies and responsibilities of a project?

The correct answer is C. Project quality management. See the full explanation below for the reasoning.

Question

Which of the processes includes all activities of the performing organization that determines policies and responsibilities of a project?

Options

  • APerformance quality control
  • BPerformance plan management
  • CProject quality management
  • DQuality control management

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    9% (3)
  • C
    77% (27)
  • D
    11% (4)