CSSLP · Question #59
What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?
The correct answer is C. Configuration Management System. The Configuration Management System is responsible for evaluating, testing, and documenting changes made to project scope and other baselines.
Question
What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?
Options
- AProject Management Information System
- BIntegrated Change Control
- CConfiguration Management System
- DScope Verification
How the community answered
(23 responses)- B4% (1)
- C91% (21)
- D4% (1)
Why each option
The Configuration Management System is responsible for evaluating, testing, and documenting changes made to project scope and other baselines.
A Project Management Information System (PMIS) is a broader system for managing project data and processes, not specifically for configuration control.
Integrated Change Control is the overall process for reviewing and approving changes, but the Configuration Management System is a specific component within this process that handles documentation and control of configured items.
The Configuration Management System is a component of the project management system that manages product and service configurations, including identifying baselines, controlling changes, and tracking their implementation and documentation.
Scope Verification is the process of formalizing acceptance of completed project deliverables, not the system for managing changes to the scope.
Concept tested: Project Configuration Management System role