CSSLP · Question #130
CSSLP Question #130: Real Exam Question with Answer & Explanation
The correct answer is A: It detects and responds to incidents properly.. The 'Do' phase of the PDCA cycle involves implementing the planned activities and controls, including incident detection and response, resource management, security awareness training, and operating the chosen controls.
Question
Which of the following activities are performed by the 'Do' cycle component of PDCA (plan-do- check-act)? Each correct answer represents a complete solution. Choose all that apply.
Options
- AIt detects and responds to incidents properly.
- BIt determines controls and their objectives.
- CIt manages resources that are required to achieve a goal.
- DIt performs security awareness training.
- EIt operates the selected controls.
Explanation
The 'Do' phase of the PDCA cycle involves implementing the planned activities and controls, including incident detection and response, resource management, security awareness training, and operating the chosen controls.
Common mistakes.
- B. Determining controls and their objectives is part of the 'Plan' phase, where goals are set and strategies are formulated, rather than the 'Do' (implementation) phase.
Concept tested. PDCA cycle 'Do' phase activities
Topics
Community Discussion
No community discussion yet for this question.