CSSLP · Question #310

Henry is the project manager of the QBG Project for his company. This project has a budget of $4,576,900 and is expected to last 18 months to complete. The CIO, a stakeholder in the project, has intro

Sign in or unlock CSSLP to reveal the answer and full explanation for question #310. The question stem and answer options stay visible for context.

Secure Software Lifecycle Management

Question

Henry is the project manager of the QBG Project for his company. This project has a budget of $4,576,900 and is expected to last 18 months to complete. The CIO, a stakeholder in the project, has introduced a scope change request for additional deliverables as part of the project work. What component of the change control system would review the proposed changes' impact on the features and functions of the project's product?

Options

  • AConfiguration management system
  • BScope change control system
  • CCost change control system
  • DIntegrated change control

Unlock CSSLP to see the answer

You've previewed enough free CSSLP questions. Unlock CSSLP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Configuration Management#Change Control#Software Development Lifecycle
Full CSSLP Practice