The correct answer is C: Risk management plan. The Risk Management Plan is the project management plan that most likely directs the quantitative risk analysis process, as it outlines the approach for all risk management activities.

Secure Software Lifecycle Management

Question

What project management plan is most likely to direct the quantitative risk analysis process for a project in a matrix environment?

Options

  • ARisk analysis plan
  • BStaffing management plan
  • CRisk management plan
  • DHuman resource management plan

Explanation

The Risk Management Plan is the project management plan that most likely directs the quantitative risk analysis process, as it outlines the approach for all risk management activities.

Common mistakes.

  • A. A 'risk analysis plan' is not a standard project management plan document; risk analysis is an activity defined within the broader risk management plan.
  • B. A Staffing management plan focuses on how project team members will be acquired, managed, and released, not on directing risk analysis processes.
  • D. A Human resource management plan (now typically referred to as Resource Management Plan) addresses team acquisition, development, and management, not the detailed approach to risk analysis.

Concept tested. Project Management - Risk Management Plan

Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/risk-management-plan

Topics

#Risk Management Plan#Project Management#Quantitative Risk Analysis#Software Lifecycle Management

Community Discussion

No community discussion yet for this question.

Full CSSLP PracticeBrowse All CSSLP Questions