CSSLP · Question #139

CSSLP Question #139: Real Exam Question with Answer & Explanation

Sign in or unlock CSSLP to reveal the answer and full explanation for question #139. The question stem and answer options stay visible for context.

Secure Software Lifecycle Management

Question

Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months. Management asks Billy how often the project team is participating in risk reassessment in this project. What should Billy tell management if he's following the best practices for risk management?

Options

  • AProject risk management happens at every milestone.
  • BProject risk management has been concluded with the project planning.
  • CProject risk management is scheduled for every month in the 18-month project.
  • DAt every status meeting the project team project risk management is an agenda item.

Unlock CSSLP to see the answer

You've previewed enough free CSSLP questions. Unlock CSSLP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk management#Project management#Continuous risk management#Risk reassessment