CSSLP · Question #10
You work as a project manager for BlueWell Inc. You are working on a project and the management wants a rapid and cost-effective means for establishing priorities for planning risk responses in your p
The correct answer is A. Qualitative risk analysis. Qualitative risk analysis is the most rapid and cost-effective method for establishing priorities for planning risk responses, as it relies on subjective assessment and ranking of risks.
Question
You work as a project manager for BlueWell Inc. You are working on a project and the management wants a rapid and cost-effective means for establishing priorities for planning risk responses in your project. Which risk management process can satisfy management's objective for your project?
Options
- AQualitative risk analysis
- BHistorical information
- CRolling wave planning
- DQuantitative analysis
How the community answered
(22 responses)- A73% (16)
- B5% (1)
- C9% (2)
- D14% (3)
Why each option
Qualitative risk analysis is the most rapid and cost-effective method for establishing priorities for planning risk responses, as it relies on subjective assessment and ranking of risks.
Qualitative risk analysis assesses and prioritizes individual project risks by evaluating their probability of occurrence and impact, often using subjective judgments and expert opinion. This process is rapid and cost-effective because it does not require complex numerical data or extensive modeling, allowing for quick prioritization of risks that warrant further attention.
Historical information serves as an input for risk identification and analysis but is not a distinct risk management process for prioritizing responses.
Rolling wave planning is a project planning technique involving progressive elaboration, not a risk management process for prioritizing risks.
Quantitative risk analysis numerically analyzes the effect of risks on project objectives, which is more time-consuming and costly due to its reliance on statistical analysis and modeling.
Concept tested: Qualitative risk analysis in project management
Source: https://www.pmi.org/learning/library/qualitative-vs-quantitative-risk-analysis-7058