Compute the Process Sigm Which DPMO should you use? Why? Answer: Process sigma assuming a 1.5 sigma shift in the mean for the empirical DPMO of 11,200 is 3.1 to 3.2. Process sigma assuming a 1.5 sigma

Sign in or unlock CSSGB to reveal the answer and full explanation for question #48. The question stem and answer options stay visible for context.

Measure Phase

Question

Compute the Process Sigm Which DPMO should you use? Why? Answer:

Process sigma assuming a 1.5 sigma shift in the mean for the empirical DPMO of 11,200 is 3.1 to 3.2. Process sigma assuming a 1.5 sigma shift in the mean for the theoretical DPMO of 48,000 is 3.7 to 3.8. Neither DPMO should be used because the process is not stable. A process sigma calculation is not appropriate for this process at this time.

Options

  • AProvide better procedures for customer service personnel
  • BRestrict access to customer data
  • CHave supervisors available to answer more questions
  • DUtilize employee involvement